Project Date: 2010

Client: Government of Nunavut

Location: Pangnirtung, Nunavut

Category: Government, Healthcare

About this Project

Pangnirtung Health Centre

The Community of Pangnirtung had identified the need for a new centre almost 10 years prior to construction. The old Pangnirtung Health Centre, constructed in the 1970s, was a smaller building that lacked the space for staff and patients in the face of a growing population.

The Health Centre is not short on space, approximately 1834 square metres on two floors. Mattina Mechanical Limited scope of work included site works, steel structure, wood framing, architectural finishes, mechanical and electrical works, medical equipment & furniture, including a diesel generator installation complete with fuel piping, and fuel storage.